Work on the Z has continued for the last two days.  Sparky spent some quality time on Friday, and there are tags and new wires all over the place.  Torch and I did some work today.  Torch focus on the exhaust system.  Pipe cutting, fitting and welding was the bulk of his work.  Work on the fuel and oil cooling system kept me busy.  In general a good work weekend.

However, we are still a bit away in getting the engine started. Here is the Items that needing to be completed to test the motor:

Engine mounts
Done

Transmission cross member
Done

Cooling system

Have parts
Oil cooling system
Done

Break boost into intake manifold

Need Parts
Air intake line

Need parts
Exhaust system
80%
Need additional parts.
Master and slave clutch

Have parts
Throttle setup

Electrical connection
Fuel line hookup

Have parts
Starter hookup

Relocated and mounted.
Alternator/power steering belt sized and changed

On Order
Power steering lines

Need to install
Drive line

On Order
Electrical system